CABINET HEATERS INSTALLATION, COMMISSIONING, OPERATION AND SERVICE MANUAL
46 of 85
Figure 20: Oil-Fired Heaters Control Box Sequence
10.8.2 Sequence of Operation
The operating sequence is as follows:
With the external controls on and calling for heat,
the burner fan and electric ignition will switch on.
After a combustion air purge of approximately twelve
seconds, the oil solenoid valve will open and the
burner will fire. After another five seconds, the
electric ignition is turned off and the burner will go
into its normal run position. The photo cell
continuously monitors the safe presence of the
flame. When the temperature control is satisfied, the
control box will turn off all its outputs simultaneously
and return to the rest position for the beginning of
the next sequence.
10.8.3 Fault Conditions
If at any stage during normal running the photo
electric cell fails to detect the flame, the control will
switch off and make an instant restart attempt. If the
flame signal is still missing, "lockout"
will occur.
If the flame is not detected by the photo cell during a
normal start, there will be no restart attempt and
"lockout" will occur in approximately 17 seconds
after the start.
If a flame is detected during the first 12 seconds
(purge), the solenoid valve will not open and the
control will "lockout". For the control sequence, see
Page 46, Figure 20.
10.8.4 Switching On
Turn on the heater with the external controls. (Heat
ON). If the "Lockout Reset" button is illuminated,
press to reset. The combustion air fan and electric
ignition should work immediately. Vent the burner oil
pump at the same time by loosening the pump vent
port (pump must be running). If the burner goes into
"lockout" before the pump has vented, wait one
minute, then reset the control box and repeat
Section 10.8.4 until all the air has been vented from
the pump and the bu rner fires.
NOTE: The burner plug and socket may be used to
turn off the burner during commissioning.
10.8.5 Blocked Flue
A safety device which measures the combustion
chamber and flue is fitted on this heater. if the
pressure exeeds the factory set maximum pressure
limit, the heater will fail safe and prevent the burner
from firing. In the event of this happening one
indicator lamp located on the front of the heater will
be illuminated - This fault should be investigated by
a competent person.
10.8.6 Adjust Burner Oil Pressure
Adjust the burner oil pressure to the value in the
data table for the burner reference letter and burner
manufacturer's information for details of the burner
oil pump. When completed, turn off burner and
remove test ga
uge and refit plug.
10.8.7 Set Combustion Air
The combustion air must be set. Measure the
emissions in the flue at a point within one metre from
the outlet of the heater and adjust for the highest
carbon dioxide (CO2) levels obtainable, usually 10.5
- 11.0%, while making little or no smoke (smoke
number 0-1). The test must be carried out with all
covers fitted and after the heater has been running
for 15 minutes.
10.8.8 Complete the Commissioning
Test the burner for correct start and stop operation
several times. Check that all safety devices operate
Always disconnect the power supply before installing or removing the control unit. Do not
attempt to open or carry out repairs on the control unit.